Ghana

  • Campaign status:
  • = Off Track
  • = At Risk
  • = On Track
Campaign yearITN distribution yearITN distribution date (current plan)Campaign rollout strategyCurrent campaign planning phaseCampaign status based on currently planned datesReason for status if At Risk/Off TrackGeographic scope (State/Region/Province)Geographic scope (district)Target populationTotal ITNs neededNet typeITN Funding partnerCampaign digital data collectionScale of digital data collectionLast updated
2021April-December 2021Sub-national phasedImplementation Not applicableNationalNational16,225,716Multi productMultipleYesFull deployment8-Nov-2021
2021July 2021Complete Not applicableAhafo361,761PBO ITNGlobal FundYesFull deployment
2021March 2022Not started OtherAshanti274,708PBO ITNGlobal FundYesFull deployment
2021March 2022Not started OtherAshanti3,100,917Standard LLINGlobal FundYesFull deployment
2021July 2021Complete Not applicableBono652,735PBO ITNGlobal FundYesFull deployment
2021July 2021Complete Not applicableBono East70,634PBO ITNGlobal FundYesFull deployment
2021July 2021Complete Not applicableBono East597,747Standard LLINGlobal FundYesFull deployment
2021June 2021Complete Not applicableCentral1,091,978PBO ITNGlobal FundYesFull deployment
2021June 2021Complete Not applicableCentral431,032Standard LLINGlobal FundYesFull deployment
2021November 2021Implementation Not applicableEastern781,242PBO ITNGlobal FundYesFull deployment
2021November 2021Implementation Not applicableEastern1,124,024Standard LLINGlobal FundYesFull deployment
2021November 2021Implementation Not applicableGreater Accra2,472,836Standard LLINGlobal FundYesFull deployment
2021April 2021Complete Not applicableNorthern606,838PBO ITNPMIYesFull deployment
2021April 2021Complete Not applicableNorthern315,042Standard LLINPMIYesFull deployment
2021April 2021Complete Not applicableNorthern East40,597PBO ITNPMIYesFull deployment
2021March 2021Complete Not applicableOti273,682PBO ITNPMIYesFull deployment
2021March 2021Complete Not applicableOti176,218Standard LLINPMIYesFull deployment
2021April 2021Complete Not applicableSavannah184,556PBO ITNPMIYesFull deployment
2021April 2021Complete Not applicableSavannah165,888Standard LLINPMIYesFull deployment
2021April 2021Complete Not applicableUpper East647,650Standard LLINPMIYesFull deployment
2021November 2021Implementation Not applicableVolta339,398PBO ITNGlobal FundYesFull deployment
2021November 2021Implementation Not applicableVolta779,670Standard LLINGlobal FundYesFull deployment
2021October 2021Implementation Not applicableWestern326,070Standard LLINGlobal FundYesFull deployment
2021October 2021Implementation Not applicableWestern794,541Dual AI ITNGlobal FundYesFull deployment
2021June 2021Complete Not applicableWestern North429,059Dual AI ITNGlobal FundYesFull deployment

While all efforts are being made to ensure that the information in the ITN Mass Campaign Tracker is up to date, it is possible that errors will be identified when viewing the information. In this case, please send an email to robert.opoku@ifrc.org or marcy.erskine@ifrc.org and the information will be immediately corrected.